The Old Tafo Municipal Assembly under the Ghana Secondary Cities Support Programme (GSCSP) undertook a sod-cutting ceremony on the 5th of February 2024 for the following UDG-3 sub-projects.
i. Lot 1: - Construction of 3.0M × 1.5M × 520M storm drain for Old Tafo Municipal Assembly at Pankrono
ii. Lot 2: - Construction of 1.5M × 1.5M × 160M storm drain for Old Tafo Municipal Assembly at Tafo Abed
iii. Lot 3: - Construction of 2.5M × 2.0M × 240M storm drain for Old Tafo Municipal Assembly at Tafo Mosque
iv. Lot 4: - Construction of 2.0M × 1.5M × 190M storm drain for Old Tafo Municipal Assembly at Tafo Ahenbronum
The sod-cutting ceremony was aimed at introducing the contractors to site and create the communities awareness about the benefit of the projects. The ceremony was honored by several dignitaries and guests, notable ones include; MP for the Old Tafo, the MCE, MCD, a representative for Nana Tafohene, Chief Imam, and the Zongo Chief. The expected period of completion is 4 months. These projects symbolized the commitment to a resilient and flood-free future.